Somerset Energy Park

Project information, progress and how to register to have your say: https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110039

 

 

Zonal Map of the proposed project

In the early stages of the project, residents can contact the applicant to arrange a meeting. The contact details are:

Further information about Somerset Energy Park is available on the project website: 
www.somersetenergypark.co.uk. 


You can also contact the project team by email at info@somersetenergypark.co.uk or by calling 
the project Freephone line on 0800 082 0906.

 

The key timings are currently:

Week commencing 19th October 2026 – Environmental Impact Assessment (EIA) Scoping Report submitted to the Planning Inspectorate (a copy will be published on the project website).
Autumn/winter 2026/27 – ongoing stakeholder engagement, environmental assessment, and further development of the proposals.
Early 2027 – public consultation on the emerging proposals, giving local communities the opportunity to view the plans, ask questions and provide feedback.
Spring 2027 – consultation feedback considered as the design is refined.
Autumn 2027 – anticipated submission of the DCO application to the Planning Inspectorate.

 

Residents are encouraged by the applicant to complete a feedback form, as it will give a valuable insight into how the community uses and engages with the land:

^